Completed Project

District-Wide Flow Measurement & Telemetry

Installation of calibrated measurement structures and telemetry at 38 locations throughout the canal system.

Project Overview

Accurate measurement is the foundation of equitable allocation. This program installed calibrated flumes, weirs and acoustic meters at the head of each primary lateral, with data logged and transmitted to the District office each hour.Staff use the resulting record to balance canal operations, verify deliveries against water orders, and report diversions to the Rio Grande Watermaster.

Timeline

  1. February 2023

    Site survey and structure selection

  2. October 2023

    First 20 sites installed and calibrated

  3. November 2024

    Program complete; all 38 sites reporting

Photo Gallery

Project Details

Status
Start
February 2023
Completion
November 2024
Location
Main Canal and 14 primary laterals
Funding
Texas Water Development Board and District funds