Main Canal Concrete Lining — Phase IV

Concrete lining of 3.6 miles of earthen main canal to eliminate seepage losses and stabilize delivery capacity to downstream laterals.

Project Overview

Phase IV continues the District’s long-term program of replacing earthen canal sections with slip-formed concrete lining. Seepage testing along this reach measured losses of more than 15 percent of flow between the upstream and downstream measurement points during the summer irrigation season.The lined section restores design capacity, allows higher flow velocities without bank erosion, and reduces the vegetation control and dredging required each year. Work is sequenced during the winter low-demand period so that deliveries to accounts served by the reach are not interrupted during peak season.New measurement structures and staff gauges are installed at each lateral turnout along the reach, improving the accuracy of the water accounting reported to the Rio Grande Watermaster.

Timeline

  1. January 2026

    Board awarded construction contract

  2. June 2026

    Canal dewatered; earthwork and subgrade preparation began

  3. November 2026

    Mile 4.2 to Mile 5.9 lining complete and returned to service

  4. December 2027

    Anticipated substantial completion

Photo Gallery

Project Details

Status
Start
June 2026
Completion
December 2027 (estimated)
Location
Main Canal, Mile 4.2 to Mile 7.8, north of Edinburg
Funding
Texas Water Development Board Agricultural Water Conservation Grant and District funds