Active Project

Lateral 9 Buried Pipeline Conversion

Replacement of 2.1 miles of open earthen lateral with 48-inch buried pipeline, recovering right-of-way and eliminating evaporation losses.

Project Overview

Open laterals in developed areas are costly to maintain and vulnerable to trash, encroachment and evaporation. This project replaces the Lateral 9 open channel with buried reinforced concrete pipe sized to carry the full design flow of the lateral.Turnouts are rebuilt with gated risers and propeller meters so that each account receives a measured delivery. The recovered right-of-way is restored and remains under District easement for access and future maintenance.

Timeline

  1. December 2025

    Design and easement verification complete

  2. March 2026

    Pipe delivery and trenching began at the Main Canal end

  3. September 2026

    First mile placed in service

  4. February 2027

    Anticipated completion and right-of-way restoration

Photo Gallery

Project Details

Status
Start
March 2026
Completion
February 2027 (estimated)
Location
Lateral 9, from the Main Canal south to FM 1925
Funding
USDA Natural Resources Conservation Service cost share and District funds